FW: decide which systems to connect to battery



 > From: Robert
 > Date: Wed, 15 Jun 2022 17:07:59 -0700
 >
 > I'll re-review this in more detail later, but, at first glance, this
 > looks correct.
 > 
 >  > From: Production Simply Solar <http://www.simplysolar.com/~production>
 >  > Date: Wed, 15 Jun 2022 16:06:06 -0700
 >  >
 >  > Hi Rob,
 >  > 
 >  > Now that we've completed your site inspection, your project has
 >  > moved to the engineering stage and is with our designers. The
 >  > turnaround time is about 2-3 weeks to produce a plan set. You can
 >  > expect to hear from one of our designers at that time. If
 >  > there are any issues or comments regarding your proposed system,
 >  > our designer will be in touch. 
 >  > 
 >  > I also have to tell you how liberating it was to see a properly
 >  > labeled main service panel (photo attached). You also knew exactly
 >  > which breakers you wanted to back up and I only hope all my clients
 >  > are as easy as you are! This list below is the breakers I believe
 >  > you want to back up. Please let me know if these are not
 >  > correct. If so, I will draft up a change order to add the four
 >  > extra breakers for backup. Additionally, if you back up
 >  > eight breakers you will need to load manage. This means in the
 >  > event of a power outage, you will need to flip on and off crucial
 >  > breakers you are and are not using to avoid your system from
 >  > drawing too much power. If the inverter draws too much power, it
 >  > will malfunction and shut down. As long as you know this, you are
 >  > good to back up the breakers of your choosing.
 >  > 
 >  > 1. #6 Kitchen outlets
 >  > 2. #10 Kitchen outlets
 >  > 3. #2 Bedrooms and bathroom outlets
 >  > 4. #4 Living, dining, and kitchen outlets
 >  > 5. #3 Living, kitchen, dining room lighting
 >  > 6. #1 Bedrooms and hallway lighting
 >  > 7. #18 Lighting Bathroom
 >  > 8. #8 Microwave
 >  > As always, please feel free to reach out with any questions or concerns.     
 >  > Thank you,
 >  > Ally Basham  Sr Project Coordinator 
 >  > Production Department  | Simply Solar
 >  > 
 >  > (707) 285-7037 ,tel:7072857037,  